watch out crown fiber is setting up shop in austin also........
there goes the pricing........
>IS this Channels Prices or Jim Seabo/Irwin
>
>>Can you tell me who to contact for the Austin work? Thanks
>>
>>>all beware
>>>
>>>>ANYONE WANT TO GO TO AUSTIN THIS WILL HELP YOU GET THE BEST PRICE (PITTSBERG ST LOUIS AND HOUSTON INSTALLS NEXT WEEK
>>>>Channel Master Price List Aerial Austin Texas		
>>>>201	Strand	
>>>>	per strand foot easement.44	
>>>>	per strand foot street 0.38	
>>>>202	Cable	
>>>>	per CBS ft. easement 0.57	
>>>>	per CBS ft. street 0.48	
>>>>203	Additional Cable	
>>>>	each additional cable per CBS ft easement 0.24	
>>>>	each additional cable per CBS ft street 0.20	
>>>>204	Splice Tap	
>>>>	per each (easement) 25.00	
>>>>	per each (street) 21.00	
>>>>205	Splice Coaxial Splitter	
>>>>	per each easement 34.00	
>>>>	per each street $29.00	
>>>>206	Over lash Coax	
>>>>	Over lash per CBS ft easement $0.62	
>>>>	Over lash per CBS ft street $0.53	
>>>>	each additional cable per CBS ft easement $ 0.24
>>>>	each additional cable per CBS ft street $0.20	
>>>>207	Delash	
>>>>	Delash per CBS ft easement $0.41	
>>>>	 Delash per CBS ft street $0.37	
>>>>208	delash/relash	
>>>>	delash/relash per CBS ft easement $0.56	
>>>>	 delash/relash per CBS ft street $0.50	
>>>>209	Tree Trimming	
>>>>	Tree Trimming per ft. easement $0.25	
>>>>	tree Trimming per ft. street $0.21
>>>>	
>>>>	Channel Master Price List Austin Texas Underground
>>>>101	Directional drill - Dirt	
>>>>	per ft. easement $13.00
>>>>	per ft. street $11.00
>>>>102	Directional drill - Rock
>>>>	per ft. easement $28.00
>>>>	per ft. street $22.00
>>>>103	Hand Trenching 18 Inches -Dirt 
>>>>	trench 18" hand - dirt easement $5.50
>>>>	trench 18" hand - dirt street $4.50
>>>>104	Hand Trenching 24 Inches -Dirt 
>>>>	trench 24" hand - dirt easement $6.50
>>>>	trench 24" hand - dirt street $5.50
>>>>105	Hand Trenching 36 Inches -Dirt 
>>>>	trench 36" hand - dirt easement $8.00
>>>>	trench 36" hand - dirt street $7.00
>>>>106	Hand Trenching 18 Inches -Rock 
>>>>	trench 18" hand - rock easement $8.00
>>>>	trench 18" hand - rock street $6.50
>>>>107	Hand Trenching 24 Inches -Rock 
>>>>	trench 24" hand - rock easement (.50
>>>>	trench 24" hand - rock street $8.00
>>>>108	Hand Trenching 36 Inches -Rock 
>>>>	trench 36" hand - rock easement $ 11.00
>>>>	trench 36" hand - rock street $ 9.50
>>>>109	Machine Trenching 18 Inches -Dirt 
>>>>	trench 18" machine - dirt easement $4.50
>>>>	trench 18" machine - dirt street  $3.50
>>>>110	Machine Trenching 24 Inches -Dirt 
>>>>	trench 24" machine - dirt easement $ 5.25
>>>>	trench 24" machine - dirt street $4.25
>>>>111	Machine Trenching 36 Inches -Dirt 
>>>>	trench 36" machine - dirt easement $6.00
>>>>	trench 36" machine - dirt street $ 5.00
>>>>112	Machine Trenching 18 Inches -Rock 
>>>>	trench 18" machine - rock easement $ 6.75
>>>>	trench 18" machine - rock street $ 5.75
>>>>113	Machine Trenching 24 Inches -Rock 
>>>>	trench 24" machine - rock easement $ 8.00
>>>>	trench 24" machine - rock street $ 7.00
>>>>114	Machine Trenching 36 Inches -Rock 
>>>>	trench 36" machine - rock easement $ 9.25
>>>>	trench 36" machine - rock street $ 8.25
>>>>115	Missile Boring
>>>>	Up to 2" conduit boring easement $ 7.00
>>>>	Up to 2" conduit boring street $ 6.00
>>>>	Up to 4" conduit boring easement $ 9.50
>>>>	Up to 4" conduit boring street $ 8.00
>>>>116	Asphalt Cut Composite
>>>>	per LT ft easement $14.50
>>>>	per LT ft street $ 12.00
>>>>117	Additional 12" Asphalt Patch
>>>>	per LT ft easement $ 4.50
>>>>	per LT ft street $ 3.00
>>>>118	Additional Conduit
>>>>	Conduit Adder easement $0.60
>>>>	Conduit Adder street $0.45
>>>>119	Set Amp Pedestal - Dirt
>>>>	each easement $ 47.00
>>>>	each street $ 40.00
>>>>120	Set Amp Pedestal - Rock
>>>>	each easement $ 65.00
>>>>	each street $ 55.00
>>>>121	Set Amp Pedestal with 5' Trench From Riser Pole - Dirt
>>>>	each easement $ 77.00
>>>>	each street $ 65.00
>>>>122	Set Amp Pedestal with 5' Trench From Riser Pole - Rock
>>>>	each easement $120.00
>>>>	each street $100.00
>>>>123	Set 8" Bullet Pedestal - Dirt
>>>>	each easement $20.00
>>>>	each street $ 17.00
>>>>124	Splice  (22 ga) Splice copper pair to normal Bell standards
>>>>	per splice easement $1.50
>>>>	per splice street $ 1.30
>>>>125	Splice  (19 ga) Splice copper pair to normal Bell standards
>>>>	per splice easement $ 1.60
>>>>	per splice street $1.40
>>>>126	Place Closure for Copper Splice
>>>>	each easement $60.00
>>>>	each street
>>>>
>>>>  
>>>>  
    