In a retro fit enviroment using existing strand, you as the Pro splilcer should make sure it is complete. Active locations are a given it is the splicers job unless otherwise stated.
If bonding was not done in the old plant properly and you are doing an excessive bonding at non active locations weather it be Eols, continuity, I would ask for a price from the contractor or MSO and at the least GET SOMETHING ON PAPER as to who's responsibility it is if you are not doing them.
Before starting any splicing project I make sure I know as well as the MSO what the Specs are and who is responsible for what.You are a fool not to as Time = Money.